PlannerPERT estimator

Jobsite PERT Estimator

Estimate
Tracking progress

Scope of work

Best / Likely / Worst for each step
How the numbers work

For each step you give three guesses. PERT weights the likely case 4×: Expected = (Best + 4×Likely + Worst) ÷ 6, and the spread is σ = (Worst − Best) ÷ 6.

After lists the steps that must finish first (e.g. 2,3). Blank means it can start day one. The longest chain is the critical path; its spread sets schedule risk. Cost spread adds up across every step.

Tracking: enter % done and dollars spent per step. Earned value = expected cost × % done. The forecast re-runs PERT on the work that is left, starting from the status date, and adds what you've already spent.

Confidence levels assume a normal distribution. When two chains are nearly the same length, real schedule risk is a bit higher than shown. Template prices are regional placeholders; replace them with your own.

Days @ 90%
–
Quote
–